Sub-Series 6: Volumes 100- 199 -- Writ Petition 319/1994 : Narmada Bachao Andolan v. Union of India and Others (1994)
Petitioners - Petitioner's Compilation II-Compilation of extracts from selected documents on records, January 1999
Marked as Volume 109. Consists of compilation of extracts from selected documents on record.
Respondents - Written Submission on behalf of Union of India, undated
Studies and Activities: Environmental Aspects of Sardar Sarovar and Narmada Sarovar projects- Narmada Control Authority, November 1998
Marked as Volume 111A. Consists of an annexure to note-2, in the form of this report by the Narmada Control Authority on "Studies and Activities: Environmental Aspects of Sardar Sarovar and Narmada Sagar Projects"
Narmada Control Authority- Resettlement and Rehabilitation Sub-group- Minutes of Forty- Third Meeting, January 1999
Marked as Volume 111B. Consists of an annexure; in the form of the minutes of the Resettlement and Rehabiliation sub-group of the Narmada Control Authority held at New Delhi on 6 January, 1999.
Sardar Sarovar Project-Report of the 18th field visit of Rehabilitation committee of Narmada Control Authority to Resettlement and Rehabilitation sites in Gujarat, 17 - 19 April 1998
Marked as Volume 111C. Consists of an annexure, in the form of a report of the 18th Field Visit of the Rehabilitation Committee of Narmada Control Authority to resettlement and rehabiliation (R&R) sites in Gujarat from 17th to 19th April, 1998.
Sardar Sarovar Project- Report of the 19th field visit of Rehabilitation Committee of Narmada Control Authority to Resettlement and Rehabilitation Sites and a submergence village in Gujarat, January 1999
Marked as Volume 111D. Consists of an annexure, in the form of a report of the 19th Field Visit of the Rehabilitation Committee of Narmada Control Authority to resettlement and rehabiliation (R&R) sites and a submergence village in Gujarat from 7th to 9th October, 1998.
Respondents - Compilation No. 1 of Government of Gujarat and Sardar Sarovar Narmada Nigam Ltd., February 1999.
Part 1 of volume marked as Volume 112. Consists of a compilation on behalf of the Government of Gujarat and Sardar Sarovar Nigam Limited. Documents pertain to review of status of resettlement and rehabilitation measures at 85 m; position of resettment at an elevation of 90 m, 110 m and 138.68 m; re: master plan and initial R&R plan; identification of land; additional rehabilitation villages (61 R&R sites) and re : time taken in seeking various clearances.
Respondents - Compilation No. 2 of Government of Gujarat and Sardar Sarovar Narmada Nigam Ltd., February 1999.
Part 2 of volume marked as Volume 112. Consists of a compilation on behalf of the Government of Gujarat and Sardar Sarovar Nigam Limited. Documents pertain to increase in number of project-affected families (PAFs) and involvement of NGOs in rehabilitation and resettlement (R&R) works.
Respondents- Compilation No. 3 of Government of Gujarat and Sardar Sarovar Narmada Nigam Ltd., February 1999.
Part 3 of of volume marked as 112. Consists of documents like summary of work done by GOG after the Supreme Court's orders/directives, approximate value of additional benefits under Gujarat R&R policy, R&R benefits to Gujarat PAFs and PAFs of other states who have resettled in Gujarat.
Respondents -Written Submission on behalf of Madhya Pradesh, 18 February 1999
Marked as Volume 113. The written submission on behalf of Madhya Pradesh. It consists of three parts - Part A, information on points desired by the Supreme Court; Part B, the written submission of Madhya Pradesh; and Part C consists of relevant extracts from the documents mentioned in index following.
Petitioners - Note in Rejoinder on Resettlement and Rehabilitation and Why further construction at this stage will be a violation of NWDT Award., 17 February 1999
Marked as Volume 114. Note in Rejoinder on resettlement and rehabilitation (R&R) and why further construction at this stage will be a violation of the Narmada Water Dispute Tribunal (NWDT) Award.
Respondents - Affidavit on behalf of the state of Gujarat / Sardar Sarovar Narmada Nigam Ltd., 9 April 1999
Marked as Volume 115. Affidavit on behalf of the State of Gujarat and the Sardar Sarovar Narmada Nigam Limited (SSNNL). Submissions pertain to constitution of Grievance Redressal Agency (GRA), status of R&R work concerning project-affected families at 85 m and beyond; reorganisation of the Sardar Sarovar Punarvasvat / Rehabilitation Agency (SSPA) et al. Annexures include undertaking of the SSPA regarding R&R activities; office orders
Petitioners - Affidavit in reponse on behalf of the Petitioners to the Affidavit on behalf of state of Gujarat/SSNNL dated 9 April 1999 and to the Report of the Grievance Redressal Authority, 18 May 1999
Petitioners - Application on behalf of Petitioners, 1 May 1999
Marked as Volume 117. Application by the Petitioners Narmada Bachao Andolan to direct the authorities, particularly the government of Gujarat to restrict height of the safety humps to the earlier size of 1.2 m and 3 m.
Respondents - Affidavit on behalf of the Government of Maharashtra, 3 May 1999
Marked as Vol 118. Affidavit on behalf of the Government of Maharashtra pertaining to various demonstrations and statements in the media of the Narmada Bachao Andolan and Medha Patkar.
Respondents - I.A. No. 12 of 1999 - An Application for direction with Affidavit, 30 April 1999
Vol 119 This consists of the interim application 12 of 1999 for directions with affidavit regarding a news item publicised in the Gujarat Age. Annexure includes the published item dated 24 April, 1999.